In Progress

Evans-Fintube Redevelopment

Located a half-mile from downtown, the Evans-Fintube site is primed to become the next major destination in Tulsa. On May 10, 2022 the Evans-Fintube Steering Committee selected Team Alchemy to develop the former industrial facility following a yearlong community-driven process. Partner Tulsa and the City look forward to turning the site into a mixed-use destination district. For additional details on the phases and current status of the project, and to view documents related to the project, see below.

4/25/22 2:01:57 PM — Drone imagery of Tulsa, Oklahoma. Photo by Shane Bevel

Project Overview

Learn more about the Evans-Fintube Redevelopment below.
Phase 1
Market Study and Feasibility Analysis
(Fall 2020-Spring 2021)
HR&A Advisors conducted stakeholder outreach and conducted a study of the market to understand priorities for development and potential uses based upon current and future market demand.
Phase 2
Request for Qualifications
(Spring-Summer 2021)
PartnerTulsa, with support from HR&A Advisors, received seven (7) proposals to an initial RFQ soliciting interest from qualified firms for redevelopment of the site. Four (4) teams were advanced to the RFP phase.
Phase 3
Request for Proposals
(Fall 2021-Winter 2022)
Three (3) teams submitted proposals, with two (2) advancing to final interviews and a presentation to community stakeholders.
Phase 4
Developer Selected
(May 2022)
On May 10, 2022, Team Alchemy was selected as the Master Developer of the site.
Phase 5
Key Terms and Development Agreement
(Estimated May 2022-December 2023)
The City, PartnerTulsa, and Team Alchemy are currently negotiating key terms for the proposed development to occur at the site. Once terms are defined, a formal contract (Development Agreement) will follow. It is estimated this phase will take 6-18 months based upon the size and scale of the proposed development.
Explore the Project

Evans-Fintube Redevelopment

Located a half-mile from downtown, the Evans-Fintube site is primed to become the next major destination in Tulsa. On May 10, 2022 the Evans-Fintube Steering Committee selected Team Alchemy to develop the former industrial facility following a yearlong community-driven process.

The Stories That Inspire Us

January 27, 2023

Trustee Highlight: Elian Hurtado

We sat down with Board member Elian Hurtado Jarve to find out about her interests, background and what she loves most about Tulsa. Elian is founder of Galera Business Consulting. As a Venezuelan immigrant living in…
Learn More
January 17, 2023

Community Partner Profile: The Tulsa Property Group Builds People-Focused Communities

Each month we highlight community members and the projects they lead. Interested in keeping up with our work? Sign up for our newsletter for monthly updates and breaking news. The Tulsa Property Group recently completed…
Learn More
January 6, 2023

Top 10 Stories of 2022

Celebrating Key Accomplishments in 2022 Tulsa experienced an unprecedented number of economic development wins in 2022, made possible through the collective work of PartnerTulsa, the City of Tulsa and our community partners. From earning $40…
Learn More

Contact Us

Casey Stowe
SVP, Finance & Real Estate casey@partnertulsa.org (918)-269-0543